PROJECTS

Taman Crude Oil Loading Terminal

Customer
Tamanneftegaz
Year
2014-2019
Location
Russia
Taman Crude Oil Loading Terminal
Electric Heating Systems
Total cable length118 000 m
Total systems output6 200 kW
Heating Systems Application
  • Drain vessels
  • Pipelines
  • Oil and mazut farm (including 40 000 m3 tank)
Skin-Effect Heating Systems
Total length heated84 000 m
Number of feeding points13
Pipes diameterfrom 22 to 1,420 mm
Maintenance temperature+5 °C …+60 °C
Transported productsWater, liquefied hydrocarbon gas, oil, oil products

Shchekinoazot Chemical Plant

Customer
Shchekinoazot Ltd.
Year
2011
Location
Russia
  • Shchekinoazot Chemical Plant
  • Shchekinoazot Chemical Plant
  • Shchekinoazot Chemical Plant
Electric Heating Systems
Total length heated 8 000 m
Total system output 410 kW
Heating Systems Application
  • Methanol M-450 producing plant
  • CFC and formalin producing plant
  • Impulse lines of Pervomayskaya power plant

United Chemical Company “Shchekinoazot” produces and sells methanol, ammonia, ammonium sulphate, caprolactam, carbamideformaldehyde concentrate (UFC), cyclohexane at domestic and foreign markets for over 60 years. SST Group electric heating systems were implemented at Shchekinoazot methanol M-450 producing plant, one of the most modern methanol producing plant on the territory of Russia, with a capacity of 450 000 tons of methanol per year. The company also provided its world-class solutions for carbamideformaldehyde concentrate (CFC) and formalin producing plant with the capacity of 50 000 tons per year. SST Group provided mineral-insulated heating cables and self-regulating heating cables.