Taman Crude Oil Loading Terminal

Customer
Tamanneftegaz
Year
2014-2019
Location
Russia
Taman Crude Oil Loading Terminal
Electric Heating Systems
Total cable length118 000 m
Total systems output6 200 kW
Heating Systems Application
  • Drain vessels
  • Pipelines
  • Oil and mazut farm (including 40 000 m3 tank)
Skin-Effect Heating Systems
Total length heated84 000 m
Number of feeding points13
Pipes diameterfrom 22 to 1,420 mm
Maintenance temperature+5 °C …+60 °C
Transported productsWater, liquefied hydrocarbon gas, oil, oil products

Shchekinoazot Chemical Plant

Customer
Shchekinoazot Ltd.
Year
2011
Location
Russia
  • Shchekinoazot Chemical Plant
  • Shchekinoazot Chemical Plant
  • Shchekinoazot Chemical Plant
Electric Heating Systems
Total length heated 8 000 m
Total system output 410 kW
Heating Systems Application
  • Methanol M-450 producing plant
  • CFC and formalin producing plant
  • Impulse lines of Pervomayskaya power plant

The complex with total capacity of 19.9 million tons per year is constructed in the South part of the Taman peninsula and has access to the Black Sea. It is intended for the transshipment of liquefied hydrocarbon gas, oil and oil products.

Tamanneftegaz (part of OTEKO group) has been successfully implementing a comprehensive investment program of Taman since the 2000s. The company has already invested more than 2 billion US dollars in the economy of the Krasnodar Territory.

Within EPC contract SST Group was responsible for electric heating systems for the Taman transshipment terminal. The project included project design, supply, supervision, installation of electric heating systems, including explosion-proof electric heaters Masterwatt, 140 control cabinets and thermal insulation. The project is still ongoing.