Total cable length | 118 000 m |
---|---|
Total systems output | 6 200 kW |
Total length heated | 84 000 m |
---|---|
Number of feeding points | 13 |
Pipes diameter | from 22 to 1,420 mm |
Maintenance temperature | +5 °C …+60 °C |
Transported products | Water, liquefied hydrocarbon gas, oil, oil products |
Total length heated | 8 000 m |
---|---|
Total system output | 410 kW |
The complex with total capacity of 19.9 million tons per year is constructed in the South part of the Taman peninsula and has access to the Black Sea. It is intended for the transshipment of liquefied hydrocarbon gas, oil and oil products.
Tamanneftegaz (part of OTEKO group) has been successfully implementing a comprehensive investment program of Taman since the 2000s. The company has already invested more than 2 billion US dollars in the economy of the Krasnodar Territory.
Within EPC contract SST Group was responsible for electric heating systems for the Taman transshipment terminal. The project included project design, supply, supervision, installation of electric heating systems, including explosion-proof electric heaters Masterwatt, 140 control cabinets and thermal insulation. The project is still ongoing.